Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works.
Comments
UPDATE - 28 April 2023
Title Registration has been achieved on Riverwalk Stage 31!
Development Victoria is in the process of notifying your conveyancer and preparations can be made for settlement by no later than Friday 12 May 2023.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 6 April 2023
Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 31 at Riverwalk.
The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by Friday 14th April 2023. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.
Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 16 March 2023
Statement of Compliance activities are continuing to be worked through with various authorities.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 24 February 2023
Statement of Compliance activities are continuing to be worked through with various authorities.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 2 February 2023
Statement of Compliance activities are continuing to be worked through with various authorities.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 23 January 2023
Your lot in Stage 31 at Riverwalk is now ready for valuation.
Please contact your bank lender to have their nominated valuer visit your lot, which can be accessed on Thursday 2nd February 2023 from 11am – 1pm. Access outside the day/times indicated above will not be possible as the fencing around Stage 31 lots will be locked.
Access for your valuer to inspect your lot is to be coordinated by scheduling a time with Clinton Gardiner (Site Foreman) on 0400 500 546 or Haris Khan (Project Manager) on 0456 788 157. Access to site is prohibited unless confirmation has been made with one of the site representatives.
Please advise your valuer to wear appropriate personal protect equipment (PPE), only utilise asphalted roads for access and to take caution when accessing your land as there may be some final construction items outstanding.
Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to riverwalk.enquiries@development.vic.gov.au
UPDATE - 19 January 2023
Construction works have now concluded on site and Practical Completion has been granted by Council. Statement of Compliance activities are continuing to progress.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 December 2022
The balance of road construction along Shanti Circuit has been completed. Wearing course asphalt is scheduled to occur in mid December, followed by line marking.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 10 November 2022
Balance road construction on Shanti Circuit is now being completed, with capping and agricultural drainage being installed. Following completion of Shanti Circuit, base course and wearing course asphalt will be completed for the Stage.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 October 2022
Concreting works are now completed and Class 2 road base and preliminary asphalt works are underway. Following completion of Class 2 road base and preliminary asphalt works, final asphalt works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 21 September 2022
NBN installation is now complete and concreting works are underway. Following completion of concreting works, Class 2 road base and road pavement prime seal works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 26 August 2022
Kerb works and electrical install are nearing completion, with NBN and footpath works to commence in the next fortnight.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 3 August 2022
Class 4 FCR, agricultural drainage and Class 3 FCR have now been completed, with kerb works and electrical install to commence in the next fortnight.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 14 July 2022
Road boxing works are now completed, with preliminary road pavement works underway as well as conduit installation. Following completion, Class 4 FCR road base and agricultural drain installation will occur.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 21 June 2022
Drainage works have now been completed and watermain works are underway. Following completion of watermain works, road boxing will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 26 May 2022
Sewer works have now been completed and drainage works are continuing to progress. Following completion of drainage works, watermain works will commence in June.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 May 2022
Sewer works have now been completed and drainage works are underway. Following completion of drainage works, watermain works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 7 April 2022
Sewer works have now been completed. Following approval of the Stage 31 road and drainage design, drainage works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 21 February 2022
Sewer works continue to progress well and are nearing completion. Following sewer works, drainage works will commence in late-February.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 6 January 2022
Bulk earthworks have now been completed. Sewer works are now underway, with drainage works to follow commencing in February 2022.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 29 November 2021
Bulk earthworks are continuing to progress well on site and are on track for completion in early-December. Following the completion of the bulk earthworks, sewer and drainage construction will commence in mid-December.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 27 October 2021
Bulk earthworks are continuing to progress well on site and are scheduled for completion in early-December. Following the completion of the bulk earthworks, sewer and drainage construction will commence in early-December.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 8th September 2021
Development Victoria is pleased to confirm that Bulk Earthwork activities are due to commence on Friday 10th September. A pre-commencement meeting has been organised with Council and all approvals granted for the subdivision works to commence. Development Victoria will continue to monitor the progress of works and update this portal as necessary.