Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works.
Comments
UPDATE - 26 September 2024
Title Registration has been achieved on Riverwalk Stage 40!
Development Victoria will be notifying your conveyancer and preparations can be made for settlement by no later than 10th October 2024.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 19 September 2024
Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 40 at Riverwalk.
The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by 1st October 2024. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.
Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 11 September 2024
Civil construction are complete onsite, Statement of Compliance activities are being worked through with Council.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 August 2024
Your lot in Stage 40 at Riverwalk is now ready for valuation.
Please contact your bank lender to have their nominated valuer visit your lot, which can be accessed on Thursday 22nd August 2024 from 10am – 1pm. Access outside the day/times indicated above will not be possible as the fencing around Stage 40 lots will be locked.
Access for your valuer to inspect your lot is to be coordinated by scheduling a time with Clinton Gardiner (Site Foreman) on 0400 500 546 or Haris Khan (Project Manager) on 0456 788 157. Access to site is prohibited unless confirmation has been made with one of the site representatives.
Please advise your valuer to wear appropriate personal protect equipment (PPE), only utilise asphalted roads for access and to take caution when accessing your land as there may be some final construction items outstanding.
Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to riverwalk.enquiries@development.vic.gov.au
UPDATE - 23 May 2024
Civil construction is complete onsite, construction of Northern Local Park is forecast to commence in the next fortnight.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 27 March 2024
Base course asphalt works are complete and electrical works will commence in early April.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 28 February 2024
Kerb and channel works are complete and base course asphalt works are underway. Following completion of the base course asphalt works, electrical works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 1 February 2024
Construction layer works are complete and road crossing conduits works are underway. Following completion of the road crossing conduits works, capping layer works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 22 December 2023
Drainage works are complete and watermain works are underway. Following completion of the watermain works, road boxing works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 22 November 2023
Sewer works are nearing completion and drainage works are underway. Following completion of the drainage works, watermain works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au