When will my land be ready?

Estimated construction completion date

August 2024

Estimated Statement of Compliance timeframe

September 2024

Estimated title registration timeframe

October 2024

Estimated settlement timeframe

October 2024

Comments

UPDATE - 27 March 2024

Base course asphalt works are complete and electrical works will commence in early April.  

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au  

 

 

 

 

UPDATE - 28 February 2024

Kerb and channel works are complete and base course asphalt works are underway. Following completion of the base course asphalt works, electrical works will commence.   

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au  

 

 

 

 

UPDATE - 1 February 2024

Construction layer works are complete and road crossing conduits works are underway. Following completion of the road crossing conduits works, capping layer works will commence.  

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au  

 

 

 

UPDATE - 22 December 2023

Drainage works are complete and watermain works are underway. Following completion of the watermain works, road boxing works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au  

 

 

 

UPDATE - 22 November 2023

Sewer works are nearing completion and drainage works are underway. Following completion of the drainage works, watermain works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

Civil Construction Progress

construction commences
75% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
In Progress
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.