When will my land be ready?

Estimated construction completion date

February 2025

Estimated Statement of Compliance timeframe

March 2025

Estimated title registration timeframe

March 2025

Estimated settlement timeframe

March 2025

Comments

UPDATE - 14 November 2024

We are pleased to provide you with an update regarding the progress of your lot in Stage 41 at Riverwalk and the revised settlement timeline.

Civil works for Stage 41 are moving forward, with recent asphalting of the internal roads now completed. While the civil construction continues, Development Victoria is coordinating with relevant stakeholders to finalise the remaining interface works and services required for the Stage 41 Statement of Compliance.

However, unforeseen challenges with the relocation of existing services to accommodate the new intersection on Geelong Road have caused delays. As a result, we have revised the expected timeline for completion of Stage 41.

We now anticipate that civil construction will be completed by February 2025, with the Statement of Compliance and settlements projected for March 2025. Please note that these dates are approximate, and we will keep you updated regularly through the Riverwalk Connect portal on any further changes.

As a reminder, settlements will occur within 14 days of title registration.

We understand that these adjustments may cause some inconvenience, and we truly appreciate your patience and continued understanding as we work to complete construction efficiently and safely.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 11 September 2024

Asphalt works are underway. Following completion of the asphalt works, line marking works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 23 May 2024

Class 4 road base works are underway. Following completion of the Class 4 road base works, kerb and channel works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 27 March 2024

Watermain works are underway. Following completion of the watermain works, road boxing works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 28 February 2024

Bulk earthworks are complete, sewer and drainage works are underway. Following completion of the sewer and drainage works, watermain works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 1 February 2024

Bulk earthworks are nearing completion and sewer works are underway. Following completion of the sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

Civil Construction Progress

construction commences
80% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
In Progress
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.