Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works.
Comments
UPDATE - 13 July 2022
Title Registration has been achieved on Riverwalk Stage 30!
Development Victoria is in the process of notifying your conveyancer and preparations can be made for settlement by no later than Wednesday 27th July 2022.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 8 July 2022
Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 30 at Riverwalk.
The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by 15th July 2022. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.
Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier.
UPDATE - 21 June 2022
Final compliance activities are in the process of being satisfied, with title registration to occur in the next fortnight.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 7 June 2022
Compliance activities are continuing to be worked through with various authorities but have been slightly delayed due to inclement weather.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 31 May 2022
Your lot in Stage 30 at Riverwalk is now ready for valuation.
Please contact your bank lender to have their nominated valuer visit your lot, which can be accessed on Friday 3rd June from 10am – 12pm. Access outside the day/times indicated above will not be possible as the fencing around Stage 30 lots will be locked.
Access for your valuer to inspect your lot is to be coordinated by scheduling a time with Clinton Gardiner (Site Foreman) on 0400 500 546 or Daniel Ponte (Project Manager) on 0437 357 967. Access to site is prohibited unless confirmation has been made with one of the site representatives.
Please advise your valuer to wear appropriate personal protect equipment (PPE), only utilise asphalted roads for access and to take caution when accessing your land as there may be some final construction items outstanding.
Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to riverwalk.enquiries@development.vic.gov.au
UPDATE - 26 May 2022
Final topsoiling works are now being completed and Statement of Compliance activities are scheduled to commence next week.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 May 2022
Electrical installation and laneway concreting is now completed, with footpath and crossover concreting and Class 2 FCR and underway. Following footpath and crossover concreting and Class 2 FCR, asphalting works and topsoiling will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 7 April 2022
Road boxing, agi drains, road crossings and Class 3 FCR works are now completed, and electrical trenching and laneway concreting is underway. Following electrical trenching and laneway concreting, Class 2 FCR and asphalting works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 21 February 2022
Drainage and watermain works have now completed, with road boxing works underway. Following road boxing, subgrade and capping works will commence in late-February.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 6 January 2022
Sewer works have now been completed. Drainage works are underway, with water and gas works to follow commencing in late-January 2022.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 29 November 2021
Bulk earthworks have now been completed. Sewer works are underway and drainage works are scheduled to commence in the next fortnight.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 27 October 2021
Bulk earthworks are continuing to progress well on site and are scheduled for completion in late-October. Following the completion of the bulk earthworks, sewer and drainage construction will commence in early-November.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 8th September 2021
Development Victoria is pleased to confirm that Bulk Earthwork activities are due to commence on Friday 10th September. A pre-commencement meeting has been organised with Council and all approvals granted for the subdivision works to commence. Development Victoria will continue to monitor the progress of works and update this portal as necessary.