UPDATE - 2 June 2023

Title Registration has been achieved on Riverwalk Stage 33! 

Development Victoria is in the process of notifying your conveyancer and preparations can be made for settlement by no later than Friday 16 June 2023.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

 

UPDATE - 23 May 2023

Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 33 at Riverwalk.

The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by 2nd June 2023. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.

Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

UPDATE - 9 May 2023

Your lot in Stage 33 at Riverwalk is now ready for valuation.

Please contact your bank lender to have their nominated valuer visit your lot, which can be accessed on Thursday 11th May 2023 from 10am – 12pm.  Access outside the day/times indicated above will not be possible as the fencing around Stage 33 lots will be locked.

Access for your valuer to inspect your lot is to be coordinated by scheduling a time with Clinton Gardiner (Site Foreman) on 0400 500 546 or Haris Khan (Project Manager) on 0456 788 157. Access to site is prohibited unless confirmation has been made with one of the site representatives.

Please advise your valuer to wear appropriate personal protect equipment (PPE), only utilise asphalted roads for access and to take caution when accessing your land as there may be some final construction items outstanding.  

Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to riverwalk.enquiries@development.vic.gov.au

 

 

UPDATE - 26 April 2023

Class 2 layer works are complete and asphalt works are underway. Following completion of asphalt works, line marking will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

 

UPDATE - 12 April 2023

Concrete works are nearing completion, Class 2 layer works are underway. Following completion of Class 2 layers works, asphalt works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

 

UPDATE - 16 March 2023

Electrical and NBN works are complete, concrete works are underway. Following completion of concrete works, Class 2 layers works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 24 February 2023

Class 4 layer works are complete, kerb and channel works are underway. Following completion of kerb and channel works, electrical and NBN works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 2 February 2023

Class 4 layer works are underway. Following completion of Class 4 layer works, kerb and channel works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 19 January 2023

Subgrade preparation and construction layer works are complete, with Class 4 layer to commence shortly.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

UPDATE - 13 December 2022

Subgrade preparation is nearing completion, with construction layer and capping layer works to commence shortly.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 10 November 2022

Watermain works are now completed and road boxing is underway. Following completion of road boxing works, subgrade preparation works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

 

UPDATE - 13 October 2022

Drainage works are now completed and watermain works are being finalised. Following completion of watermain works, road boxing and subgrade preparation works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

 

UPDATE - 21 September 2022

Drainage works are nearing completion and watermain works are underway. Following completion of watermain works, road boxing and subgrade preparation works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

UPDATE - 26 August 2022

Sewer works are now completed and drainage works are continuing to progress. Following completion of drainage works, watermain works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

UPDATE - 3 August 2022

Sewer works are now completed and drainage works are expected to begin week commencing 8th August. Following completion of drainage works, watermain works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 14 July 2022

Sewer works are continuing to progress on site and are due for completion in late-July. Drainage works have also commence on site, with completion likely in mid-August. Following completion of drainage works, watermain works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 21 June 2022

Filling works are now completed, with sewer works now underway. Following completion of sewer works, drainage works will commence on site.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 26 May 2022

Filling works are now completed, with sewer works scheduled to commence in early-June.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 13 May 2022

Filling works are nearing completion and are anticipated to be completed in mid-May. Following completion of filling works, sewer works will commence.  

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 7 April 2022

Filling works are continuing to progress well and are anticipated to be completed in late-April. Following completion of filling works, sewer works will commence.   

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.

Title Registration Progress

75%
complete

settlement
100% - In Progress

Contact made by Development Victoria to purchaser's legal representatives / conveyancers to initiate settlement process (settlement can occur at any time up to 14 days after title registration is achieved). Soil testing by builders and bank valuations can be undertaken at this point.

Title registration
75% - Complete

Document lodged to Land Titles Victoria to enable title registration. Estimated timeframe for title registration following lodgement 10-14 days.

statement of
compliance
50% - Complete

Document received from local council confirming construction has been completed in accordance with approved plans developed by the relevant authorities.