Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
In Progress
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works.
Comments
UPDATE - 11 September 2024
Bulk earthworks are complete and sewer works are underway. Following completion of the sewer works, drainage works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au