Comments

UPDATE - 12 May 2025

Title Registration has been achieved on Riverwalk Stage 42!

Development Victoria will be notifying your conveyancer and preparations can be made for settlement by no later than 26th May 2025.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 10 February 2025

Bulk earthworks are complete and sewer works are underway. Following completion of the sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 11 September 2024

Bulk earthworks are complete and sewer works are underway. Following completion of the sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water
Provision of water connection to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.

Title Registration Progress

75%
complete

settlement
100% - In Progress

Contact made by Development Victoria to purchaser's legal representatives / conveyancers to initiate settlement process (settlement can occur at any time up to 14 days after title registration is achieved). Soil testing by builders and bank valuations can be undertaken at this point.

Title registration
75% - Complete

Document lodged to Land Titles Victoria to enable title registration. Estimated timeframe for title registration following lodgement 10-14 days.

statement of
compliance
50% - Complete

Document received from local council confirming construction has been completed in accordance with approved plans developed by the relevant authorities.