When will my land be ready?

Estimated civil construction completion timeframe

May 2026

Estimated Statement of Compliance timeframe

May 2026

Estimated Title Registration timeframe

June 2026

Estimated settlement timeframe

June 2026

Comments

UPDATE - 3 MARCH 2026

We are writing to you to provide an update on the settlement timing for your purchased lot in Stage 45 at Riverwalk.

Civil construction at Stage 45 is continuing to progress well with installation of electrical and NBN services.

As civil works near completion, Development Victoria is working with relevant authorities to progress approvals before land is titled in Stage 45, which has resulted in revised estimated delivery timeframes.

Civil construction works for Stage 45 are currently forecast to be completed in May 2026, with Stage 45 title registration and settlements anticipated to occur in June 2026. Please note, the forecast timeframes are indicative only and we will provide regular updates on the Riverwalk Connect portal and eDMs to ensure the latest forecast timeframes for Stage 45 are communicated.

Please be advised that settlements are required within 14 days of title registration.

We continue to work with the relevant authorities to ensure these matters are rectified as soon as possible.

We apologise for any inconvenience this delay may cause and we thank you for your understanding and patience.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

Civil Construction Progress

construction commences
65% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water
Provision of water connection to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
In Progress
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.