UPDATE - 2 June 2026

Title Registration has been achieved on Riverwalk Stage 45!

Development Victoria will be notifying your conveyancer and preparations can be made for settlement by no later than the 16th of June 2026.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 20 May 2026

Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 45 at Riverwalk. 

The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected in the next 1-2 weeks. Please note that this timeframe is an estimate only and ultimately dependent on Land Use Victoria’s processing timeframes.

Further notification will be provided once titles have been issued. Purchasers are reminded that you have 14 days from receiving the Title Registration notification to arrange settlement, however you may arrange with your conveyancer to book an earlier settlement.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 21 April 2026

Stage 45 has achieved practical completion and your lot is now ready for a valuation inspection.

Please contact your lender to have their nominated valuer visit your lot within the following timeslots:

  • Tuesday 28th - Thursday 30th of April between 10am - 2pm; and
  • Tuesday 5th - Thursday 7th of May between 10am - 2pm.

Access outside the dates indicated above will not be possible as the fencing around the stage will be locked.

Please have your valuer notify  Clinton Gardner (0400 500 546) prior to arrival. Access will be prohibited unless prior contact has been made.

Valuers are required to wear appropriate personal protect equipment (PPE), utilise asphalted roads for access only and take caution when accessing your land as there may be some final construction items outstanding.

Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to  riverwalk.enquiries@development.vic.gov.au

UPDATE - 3 MARCH 2026

We are writing to you to provide an update on the settlement timing for your purchased lot in Stage 45 at Riverwalk.

Civil construction at Stage 45 is continuing to progress well with installation of electrical and NBN services.

As civil works near completion, Development Victoria is working with relevant authorities to progress approvals before land is titled in Stage 45, which has resulted in revised estimated delivery timeframes.

Civil construction works for Stage 45 are currently forecast to be completed in May 2026, with Stage 45 title registration and settlements anticipated to occur in June 2026. Please note, the forecast timeframes are indicative only and we will provide regular updates on the Riverwalk Connect portal and eDMs to ensure the latest forecast timeframes for Stage 45 are communicated.

Please be advised that settlements are required within 14 days of title registration.

We continue to work with the relevant authorities to ensure these matters are rectified as soon as possible.

We apologise for any inconvenience this delay may cause and we thank you for your understanding and patience.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water
Provision of water connection to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.

Title Registration Progress

75%
complete

settlement
100% - In Progress

Contact made by Development Victoria to purchaser's legal representatives / conveyancers to initiate settlement process (settlement can occur at any time up to 14 days after title registration is achieved). Soil testing by builders and bank valuations can be undertaken at this point.

Title registration
75% - Complete

Document lodged to Land Titles Victoria to enable title registration. Estimated timeframe for title registration following lodgement 10-14 days.

statement of
compliance
50% - Complete

Document received from local council confirming construction has been completed in accordance with approved plans developed by the relevant authorities.