Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works.
Comments
UPDATE - 17 May 2023
Title Registration has been achieved on Riverwalk Stage 32!
Development Victoria is in the process of notifying your conveyancer and preparations can be made for settlement by no later than Wednesday 31 May 2023.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 11 May 2023
Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 32 at Riverwalk.
The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by 22nd May 2023. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.
Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 26 April 2023
Statement of Compliance is expected to be achieved shortly.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 12 April 2023
Statement of Compliance is expected to be achieved shortly.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 16 March 2023
Construction works are complete onsite. Statement of Compliance activities are being worked through with various authorities.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 7 March 2023
Your lot in Stage 32 at Riverwalk is now ready for valuation.
Please contact your bank lender to have their nominated valuer visit your lot, which can be accessed on Wednesday 15th March 2023 from 11am – 1pm. Access outside the day/times indicated above will not be possible as the fencing around Stage 32 lots will be locked.
Access for your valuer to inspect your lot is to be coordinated by scheduling a time with Clinton Gardiner (Site Foreman) on 0400 500 546 or Haris Khan (Project Manager) on 0456 788 157. Access to site is prohibited unless confirmation has been made with one of the site representatives.
Please advise your valuer to wear appropriate personal protect equipment (PPE), only utilise asphalted roads for access and to take caution when accessing your land as there may be some final construction items outstanding.
Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to riverwalk.enquiries@development.vic.gov.au
UPDATE - 24 February 2023
Construction works are nearing completion onsite, Statement of Compliance activities are being worked through with various authorities.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 2 February 2023
Class 2 road base installation is complete, with asphalt works to be commenced shortly, followed by line marking works.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 19 January 2023
Concrete works are nearing completion, with Class 2 road base to be installed shortly. Following completion of Class 2, asphalt works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 December 2022
Electrical and NBN installation are now complete, with concrete works scheduled to be completed by the end of the calendar year. In early 2023, class 2 will be installed.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 10 November 2022
Kerb and channel and electrical cabling works are now completed and NBN works are underway. Following completion of NBN, concreting works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 October 2022
Class 4 road base and agricultural drainage installation are now completed and Class 3 road base works are underway. Following completion of Class 3 road base, kerb and channel works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 21 September 2022
Road boxing, sub-grade preparation and conduits install is now complete, with Class 4 road base and agricultural drainage installation underway. Following completion of Class 4 FCR and agricultural drainage, Class 3 road base and kerb and channel works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 26 August 2022
Watermain works are now completed and road boxing is underway. Following completion of road boxing works, sub-grade preparation and capping layer works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 3 August 2022
Sewer and drainage works are now completed and watermain works are underway. Following completion of watermain works, road boxing and sub-grade preparation will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 14 July 2022
Sewer works are continuing to progress and will be completed in the next fortnight. Drainage works are also continuing to progress and are on track for completion by late-July. Following completion of drainage works, watermain works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 21 June 2022
Sewer works are continuing to progress and will be completed shortly. Sections of drainage works have commenced and are continuing to progress on site. Following completion of drainage works, watermain works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 26 May 2022
Sewer works are continuing to progress and will be completed in early-June. Following completion of sewer works, drainage works will commence in June.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 May 2022
Sewer works are now underway and expected to be completed in early-June. Following completion of sewer works, drainage works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 7 April 2022
Filling works have now been completed, and sewer works are forecast to commence in early-April. Following completion of sewer works, drainage works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 21 February 2022
Bulk earthworks have commenced on site and are progressing well. Following bulk earthworks, sewer works will commence in early-March.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au