UPDATE - 14 August 2023

Title Registration has been achieved on Riverwalk Stage 34!

Development Victoria is in the process of notifying your conveyancer and preparations can be made for settlement by no later than 28th August 2023.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 9 August 2023

Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 34 at Riverwalk.

The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by 18th August 2023. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.

Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au    

 

 

UPDATE - 3 August 2023

Your lot in Stage 34 at Riverwalk is now ready for valuation.

Please contact your bank lender to have their nominated valuer visit your lot, which can be accessed on Wednesday 9th August 2023 from 10am – 1pm.  Access outside the day/times indicated above will not be possible as the fencing around Stage 34 lots will be locked.

Access for your valuer to inspect your lot is to be coordinated by scheduling a time with Clinton Gardiner (Site Foreman) on 0400 500 546 or Haris Khan (Project Manager) on 0456 788 157. Access to site is prohibited unless confirmation has been made with one of the site representatives.

Please advise your valuer to wear appropriate personal protect equipment (PPE), only utilise asphalted roads for access and to take caution when accessing your land as there may be some final construction items outstanding.  

Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to  riverwalk.enquiries@development.vic.gov.au    



UPDATE - 20 July 2023

Construction works are now complete onsite, Statement of Compliance activities are being worked through with relevant authorities. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 20 June 2023

Electrical and NBN works are now complete, with concrete works underway. Following completion of the concrete works, asphalt works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

UPDATE - 26 May 2023

Electrical works are now complete, with NBN works underway. Following completion of the NBN works, concrete works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

UPDATE - 26 April 2023

The construction layer, road crossing conduits and capping layer works are now complete, with agricultural drainage works underway. Following completion of the agricultural drainage works, Class 3 road base will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

UPDATE - 12 April 2023

Construction layer is complete, capping layer is underway. Following completion of capping layer, Class 3 layer works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

 

UPDATE - 16 March 2023

Road boxing is complete, subgrade preparation is underway. Following completion of subgrade preparation, construction layer will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

UPDATE - 24 February 2023

Watermain installation is underway. Following completion of watermain installation, road boxing will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

UPDATE - 2 February 2023

Drainage works are nearing completion. Following completion of drainage works, watermain installation will commence shortly.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

UPDATE - 19 January 2023

Sewer works are nearing completion and drainage works have commenced in road reserves. Following completion of drainage works, watermain installation will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

UPDATE - 13 December 2022

Sewer works are now underway and are due for completion in December. Drainage works have commenced in road reserves. Following completion of drainage works, watermain installation will commence in early 2023.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au  

 

 

 

UPDATE - 10 November 2022

Filling works are now completed on site and sewer works are underway. Following completion of sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

 

UPDATE - 13 October 2022

Filling works are now completed on site and sewer works are underway. Following completion of sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

 

UPDATE - 21 September 2022

Filling works are now completed on site and sewer works are underway. Following completion of sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

 

UPDATE - 26 August 2022

Filling works are now completed on site and sewer works are scheduled to commence in September. Following completion of sewer works, drainage works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

 

UPDATE - 3 August 2022

Filling works are now completed on site, with sewer works to commence in the 3rd week of August. Following completion of sewer works, drainage works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 14 July 2022

Filling works are continuing to progress and are still scheduled for completion in late-July. Following completion of filling works, sewer works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 21 June 2022

Filling works are continuing to progress and are still scheduled for completion in July. Following completion of filling works, sewer works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 26 May 2022

Filling works are continuing to progress and are still scheduled for completion in July. Following completion of filling works, sewer works will commence.  

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 13 May 2022

Filling works are now underway and are anticipated to be completed in early-July. Following completion of filling works, sewer works will commence.   

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.

Title Registration Progress

75%
complete

settlement
100% - In Progress

Contact made by Development Victoria to purchaser's legal representatives / conveyancers to initiate settlement process (settlement can occur at any time up to 14 days after title registration is achieved). Soil testing by builders and bank valuations can be undertaken at this point.

Title registration
75% - Complete

Document lodged to Land Titles Victoria to enable title registration. Estimated timeframe for title registration following lodgement 10-14 days.

statement of
compliance
50% - Complete

Document received from local council confirming construction has been completed in accordance with approved plans developed by the relevant authorities.