Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works.
Comments
UPDATE - 24 November 2023
Title Registration has been achieved on Riverwalk Stage 35!
Development Victoria is in the process of notifying your conveyancer and preparations can be made for settlement by no later than 8th December 2023.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 15 November 2023
Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 35 at Riverwalk.
The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by 24th November 2023. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.
Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 12 October 2023
Statement of Compliance activities are continuing to progress.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 20 September 2023
On site works are now completed and Statement of Compliance activities are continuing to progress.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 September 2023
Your lot in Stage 35 at Riverwalk is now ready for valuation.
Please contact your bank lender to have their nominated valuer visit your lot, which can be accessed on Friday 22nd September 2023 from 10am – 1pm. Access outside the day/times indicated above will not be possible as the fencing around Stage 35 lots will be locked.
Access for your valuer to inspect your lot is to be coordinated by scheduling a time with Clinton Gardiner (Site Foreman) on 0400 500 546 or Haris Khan (Project Manager) on 0456 788 157. Access to site is prohibited unless confirmation has been made with one of the site representatives.
Please advise your valuer to wear appropriate personal protect equipment (PPE), only utilise asphalted roads for access and to take caution when accessing your land as there may be some final construction items outstanding.
Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to riverwalk.enquiries@development.vic.gov.au
UPDATE - 24 August 2023
Concrete works are now complete and Class 2 layer works are underway. Following completion Class 2 layer works, asphalt works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 20 July 2023
Electrical and NBN works are complete and concrete works are now underway. Following completion of concrete works, Class 2 layer works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 20 June 2023
Subgrade preparation and construction layer works are complete and Agi drains installation is now underway. Following completion of the Agi drains installation, kerb and channel will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 26 May 2023
Road boxing is complete and subgrade preparation and construction layer works are now underway. Following completion of the construction layer works, road crossing conduits will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 26 April 2023
Drainage works are complete and watermain works are now underway. Following completion of the watermain works, road boxing will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 12 April 2023
Drainage works are nearing completion. Following completion of drainage works, watermain installation will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 16 March 2023
Sewer works are complete, drainage works are underway. Following completion of drainage works, watermain installation will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 24 February 2023
Sewer works are complete, drainage works are underway. Following completion of drainage works, watermain installation will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 2 February 2023
Sewer works are nearing completion. Following completion of sewer works, drainage works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 19 January 2023
Bulk earthworks are now complete, and sewer works are underway. Following completion of sewer works, drainage works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 December 2022
Bulk earthworks are now complete, and sewer works are scheduled to commence following the backfill works around the acoustic wall. Following completion of sewer works, drainage works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 10 November 2022
Filling works are now approx. 90% completed. Following completion of sewer works in Stage 34, the sewer works in Stage 35 will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 October 2022
Filling works are now approx. 90% completed. Following completion of sewer works in Stage 34, the sewer works in Stage 35 will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 21 September 2022
Filling works are now approx. 90% completed. Following completion of sewer works in Stage 34, the sewer works in Stage 35 will commence in October 2022.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 26 August 2022
Filling works are now approx. 85% completed. Following completion of filling works, sewer works will commence in September 2022.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 3 August 2022
Filling works are now underway and are approx. 65% completed. Following completion of filling works, sewer works will commence in September 2022.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 14 July 2022
Filling works are now underway and are approx. 50% completed. Following completion of filling works, sewer works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au