Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water
Provision of water connection to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
In Progress
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works.
Comments
UPDATE - 20 February 2025
We are writing to provide an update on the settlement progress of your purchased lot in Stage 37 at Riverwalk.
Works internal to Stage 37 are complete, and the Airforce Road and Geelong Road Intersection works are currently ongoing, which are essential for the delivery of Stage 37.
However, these intersection works have been delayed due to the relocation of authority communications infrastructure, which had to be completed before the intersection can be completed. The delays in the authority relocation works have impacted the overall timeline for obtaining Statement of Compliance for Stage 37.
As a result, the anticipated settlement timing for Stage 37 has been revised to Mid-May 2025. This is an approximate timeframe, and we will continue to provide regular updates through the Riverwalk Connect portal.
As a reminder, settlements will occur within 14 days of title registration.
We understand that this delay may cause inconvenience, and we sincerely appreciate your patience and understanding as we work to complete these essential works efficiently and safely.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 10 February 2025
Concrete works are underway. Following completion of the concrete works, asphalt works will commence. The Airforce Intersection works are underway.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 14 November 2024
We are pleased to provide you with an update regarding the progress of your lot in Stage 37 at Riverwalk and the revised settlement timeline.
Civil works for Stage 37 are moving forward, with recent asphalting of the internal roads now completed. While the civil construction continues, Development Victoria is coordinating with relevant stakeholders to finalise the remaining interface works and services required for the Stage 37 Statement of Compliance.
However, unforeseen challenges with the relocation of existing services to accommodate the new intersection on Geelong Road have caused delays. As a result, we have revised the expected timeline for completion of Stage 37.
We now anticipate that civil construction will be completed by February 2025, with the Statement of Compliance and settlements projected for March 2025. Please note that these dates are approximate, and we will keep you updated regularly through the Riverwalk Connect portal on any further changes.
As a reminder, settlements will occur within 14 days of title registration.
We understand that these adjustments may cause some inconvenience, and we truly appreciate your patience and continued understanding as we work to complete construction efficiently and safely.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 11 September 2024
Concrete works are underway. Following completion of the concrete works, asphalt works will commence. The Airforce Intersection works are underway.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 23 May 2024
Watermain works are complete and road boxing is underway. Following completion of the road boxing, subgrade preparation will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 27 March 2024
Bulk earthworks and sewer works are underway. Following completion of the sewer works, drainage works will commence.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au