When will my land be ready?

Estimated construction completion date

February 2025

Estimated Statement of Compliance timeframe

March 2025

Estimated title registration timeframe

March 2025

Estimated settlement timeframe

March 2025

Comments

UPDATE - 11 September 2024

Concrete works are underway. Following completion of the concrete works, asphalt works will commence. The Airforce Intersection works are underway.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 23 May 2024

Watermain works are complete and road boxing is underway. Following completion of the road boxing, subgrade preparation will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 27 March 2024

Bulk earthworks and sewer works are underway. Following completion of the sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

Civil Construction Progress

construction commences
70% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
In Progress
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.