UPDATE - 18 April 2024

Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 38 at Riverwalk.

The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by 29th April 2024. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.

Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

 

UPDATE - 27 March 2024

Statement of Compliance activities are being worked through with various authorities, with overall Statement of Compliance expected in April.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

 

 

UPDATE - 6 March 2024

Your lot in Stage 38 at Riverwalk is now ready for valuation.

Please contact your bank lender to have their nominated valuer visit your lot, which can be accessed on Thursday 14th March 2024 from 10am – 1pm.  Access outside the day/times indicated above will not be possible as the fencing around Stage 38 lots will be locked.

Access for your valuer to inspect your lot is to be coordinated by scheduling a time with Clinton Gardiner (Site Foreman) on 0400 500 546 or Haris Khan (Project Manager) on 0456 788 157. Access to site is prohibited unless confirmation has been made with one of the site representatives.

Please advise your valuer to take caution when accessing your land as the lots are fenced off and recently hydroseeded as a mitigation measure for dust, only utilise asphalted roads for access and to wear appropriate personal protect equipment (PPE).

Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to  riverwalk.enquiries@development.vic.gov.au 



 

UPDATE - 28 February 2024

Construction works are complete onsite, Statement of Compliance activities are being worked through with various authorities.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

 

UPDATE - 1 February 2024

Concrete works are complete, Class 2 layer works are underway. Following completion of Class 2 layer works, asphalt works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

 

UPDATE - 22 December 2023

Kerb and channel works are complete, electrical works will commence in January 2024. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

 

 

 

 

 

UPDATE - 22 November 2023

Class 3 road base works are now complete and kerb and channel works are underway. Following completion of kerb and channel works, electrical works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

 

UPDATE - 12 October 2023

Sewer works are now complete and drainage works are underway. Following completion of drainage works, watermain works will commence. 

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

 

 

UPDATE - 20 September 2023

Abatement and bulk earthworks are now complete and sewer works are underway. Following completion of sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au 

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.

Title Registration Progress

50%
complete

settlement
100%

Contact made by Development Victoria to purchaser's legal representatives / conveyancers to initiate settlement process (settlement can occur at any time up to 14 days after title registration is achieved). Soil testing by builders and bank valuations can be undertaken at this point.

Title registration
75% - In Progress

Document lodged to Land Titles Victoria to enable title registration. Estimated timeframe for title registration following lodgement 10-14 days.

statement of
compliance
50% - Complete

Document received from local council confirming construction has been completed in accordance with approved plans developed by the relevant authorities.