Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works.
Comments
UPDATE - 19 MAY 2021
Title Registration has been achieved on Riverwalk Stage 27!
Development Victoria is in the process of notifying your conveyancer and preparations can be made for settlement by no later than Wednesday 2nd June 2021.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au
UPDATE - 13 MAY 2021
Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 27 at Riverwalk.
The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by late-May 2021. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.
Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier.
If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au