Comments

UPDATE - 13 June 2024

Title Registration has been achieved on Riverwalk Stage 36!

Development Victoria will be notifying your conveyancer and preparations can be made for settlement by no later than 27th June 2024.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 3 June 2024

Development Victoria is pleased to confirm that Statement of Compliance has been issued for Stage 36 at Riverwalk. 

The Plan of Subdivision will shortly be lodged at Land Use Victoria for registration, with titles expected by 12th June 2024. Please note that this timeframe is only an estimate and dependent on Land Use Victoria.

Further notification will be provided once Titles have been issued. Purchasers are reminded that you have 14 days from Title Registration Notification to arrange settlement, however you may arrange with your conveyancer to book settlement earlier.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 23 May 2024

Statement of Compliance activities are being worked through with the final authority, with overall Statement of Compliance expected in late-May.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 27 March 2024

Statement of Compliance activities are continuing to progress, with overall Statement of Compliance expected in May.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 28 February 2024

Statement of Compliance activities are continuing to progress, with overall Statement of Compliance expected imminently.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 1 February 2024

Statement of Compliance activities are continuing to progress, with overall Statement of Compliance expected in the next fortnight.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 22 December 2023

Statement of Compliance activities are continuing to progress.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 27 November 2023

Please contact your bank lender to have their nominated valuer visit your lot, which can be accessed on Friday 1st December 2023 from 10am – 1pm.  Access outside the day/times indicated above will not be possible as the fencing around Stage 36 lots will be locked.

Access for your valuer to inspect your lot is to be coordinated by scheduling a time with Clinton Gardiner (Site Foreman) on 0400 500 546 or Haris Khan (Project Manager) on 0456 788 157. Access to site is prohibited unless confirmation has been made with one of the site representatives.

Please advise your valuer to wear appropriate personal protect equipment (PPE), only utilise asphalted roads for access and to take caution when accessing your land as there may be some final construction items outstanding.

Should you or your valuer have any queries regarding access to your lot, please send an email enquiry to riverwalk.enquiries@development.vic.gov.au

UPDATE - 22 November 2023

Construction works are now complete onsite. Statement of Compliance activities are continuing to progress.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 12 October 2023

Class 2 road base works are now complete and concrete works are underway. Following completion of concrete works, final asphalting and line marking will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 20 September 2023

Kerb, electrical and NBN installation is now complete and Class 2 road base works are underway. Following completion of Class 2 works, asphalt works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 24 August 2023

Installation of road crossing service conduits, capping layer and Class 4 and 3 layer works are now complete and kerb works are underway. Following completion of the kerb, electrical and NBN works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 20 July 2023

Subgrade preparation and construction layer works are complete and installation of road crossing service conduits is underway. Following completion of the installation of road crossing service conduits, capping layer works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 20 June 2023

Drainage works are complete and watermain installation are underway. Following completion of the watermain installation, road boxing will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 26 May 2023

Sewer works are complete and drainage works are underway. Following completion of the drainage, watermain installation will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 26 April 2023

Site preparation works are complete, sewer works are nearing completion. Following completion of sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 12 April 2023

Site preparation works are complete, sewer works are underway. Following completion of sewer works, drainage works will commence.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

UPDATE - 16 March 2023

Site preparation works are underway. Sewer works will commence in early April.

If you have any questions about the above information, please send an email to riverwalk.enquiries@development.vic.gov.au

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works.

Title Registration Progress

75%
complete

settlement
100% - In Progress

Contact made by Development Victoria to purchaser's legal representatives / conveyancers to initiate settlement process (settlement can occur at any time up to 14 days after title registration is achieved). Soil testing by builders and bank valuations can be undertaken at this point.

Title registration
75% - Complete

Document lodged to Land Titles Victoria to enable title registration. Estimated timeframe for title registration following lodgement 10-14 days.

statement of
compliance
50% - Complete

Document received from local council confirming construction has been completed in accordance with approved plans developed by the relevant authorities.